Little Sandy Bridge

Little Sandy Bridge is a pedestrian bridge located between the Nepean Cycleway at Chellaston Street, Camden and River Road Reserve, Elderslie.

Significant damage to the bridge approach and riverbank on the eastern side occurred during four flood events in 2022.

Design works are nearing completion, and Council anticipates inviting tenders Mid-January 2025.

A report to recommend the construction contract is scheduled for April 2025 with construction scheduled to commence in May 2025. 

A completion date will be confirmed once a construction contract has been awarded. 

 

Project Updates 

2022

Updated 8 November 2022

  • The design options for the rectification of Little Sandy Bridge are ongoing. Due to the number of recent floods and significant changes to the riverbank there will be additional river survey and flood modelling required. 

Updated 14 October 2022

  • The embankments and pathways adjacent to Little Sandy Bridge have been damaged further as a result of the most recent flooding 8 October 2022
  • Development of concept design options are responding to this further damage and are ongoing.

Updated 5 September 2022

  • Concept design options are still in progress and are expected to be completed by mid-September 2022.
  • Survey works and design consultants have been engaged and works are in progress.

Updated 10 August 2022

  • Survey works have been engaged and are in progress.
  • Design consultants have been engaged.
  • Concept design options are in progress and expected to be completed by mid September 2022. 

2023

Updated 3 November 2023

  • Council has confirmed the preferred rectification option.

  • Quotations are being sought from specialist design consultants to undertake the detailed design.

  • Design is scheduled to commence in December.

  • Once design proposals are received and a contract is awarded the scheduled commencement date for construction will be confirmed.

Updated 18 September 2023

  • A peer review of the concept design options for rectification of the damage to Little Sandy Bridge has been completed. Concept designs will now be completed and presented to Council in October for approval to proceed with the preferred option;  

  • Following adoption of the preferred option, Council will proceed to engage a consultant for detail design. Updates will be provided regarding timeframes expected to complete the detail design and issue a tender for construction.

Updated 13 June 2023

  • Council has completed concept design options for the rectification of the damage to Little Sandy Bridge. A peer review of the options is being undertaken before detail design commences. Further updates on timing will be provided once detailed design commences. 

Updated 21 March 2023

  • Additional survey works and flood modelling, required due to the significant changes to the river banks have been completed. This information has been used to inform a review of  and modification to the concept design options.

    Final design options and cost estimates are now completed and are being considered by Council.

    Once a preferred concept is agreed, consultants will be contracted to undertake the detailed design.

    Further updates on timing will be provided once detailed design commences.

2024

Updated December 2024

  • Procurement of the detailed design contract was undertaken between November 2023 and January 2024.
  • Following award of this contract, detailed design commenced in February and is scheduled to be completed by September 2024
  • Council anticipates inviting a request for tender for construction in January 2025.
  • A report to recommend award of the construction contract is scheduled for April 2025.
  • Construction work is scheduled to commence in May 2025.
  • A completion date will be confirmed once a construction contract is awarded.