Little Sandy Bridge
Little Sandy Bridge is a pedestrian bridge located between the Nepean Cycleway at Chellaston Street, Camden and River Road Reserve, Elderslie.
Significant damage to the bridge approach and riverbank on the eastern side occurred during four flood events in 2022.
Design works are nearing completion, and Council anticipates inviting tenders Mid-January 2025.
A report to recommend the construction contract is scheduled for April 2025 with construction scheduled to commence in May 2025.
A completion date will be confirmed once a construction contract has been awarded.
Project Updates
Updated 8 November 2022 Updated 14 October 2022 Updated 5 September 2022 Updated 10 August 2022 Updated 3 November 2023 Council has confirmed the preferred rectification option. Quotations are being sought from specialist design consultants to undertake the detailed design. Design is scheduled to commence in December. Once design proposals are received and a contract is awarded the scheduled commencement date for construction will be confirmed. Updated 18 September 2023 A peer review of the concept design options for rectification of the damage to Little Sandy Bridge has been completed. Concept designs will now be completed and presented to Council in October for approval to proceed with the preferred option; Following adoption of the preferred option, Council will proceed to engage a consultant for detail design. Updates will be provided regarding timeframes expected to complete the detail design and issue a tender for construction. Updated 13 June 2023 Council has completed concept design options for the rectification of the damage to Little Sandy Bridge. A peer review of the options is being undertaken before detail design commences. Further updates on timing will be provided once detailed design commences. Updated 21 March 2023 Additional survey works and flood modelling, required due to the significant changes to the river banks have been completed. This information has been used to inform a review of and modification to the concept design options. Final design options and cost estimates are now completed and are being considered by Council. Once a preferred concept is agreed, consultants will be contracted to undertake the detailed design. Further updates on timing will be provided once detailed design commences. Updated December 2024
2022
2023
2024